Brickwork Almost Done

Good progress has been maintained with the final push happening to get the brickwork complete. All the walls are now complete with the front porch and some window ledges to complete. From what we can see they have done an excellent job. Can't wait to see them cleaned.

I have included a couple of photos of the front and will post some more once finished and I gain access.


Saturday, 15 August 2015

Brickwork Continues and Skylight variation!!!!

Brickwork has continued with 4 week of very good weather and a couple of hours of rain that didn't stop progress. Had a site meeting yesterday to discuss having a Skylight added above the stairs as there is no window in the stairwell. Have decided to include a velux fixed skylight / window 55cm x 140cm. So we now should get a good amount of light and a view of the sky as you go up the stairs. 

It was also an opportunity to get some photos of the brickwork.

Front 

Rumpus and alfresco


Kitchen dining family room